Construction Progress Billing: AIA Style Invoicing Guide
Construction projects use progress billing — invoicing based on percentage of work completed rather than one final payment.
Schedule of Values
Before work starts, create a Schedule of Values (SOV) breaking the contract sum into line items: foundation, framing, electrical, etc.
Progress Billing Calculation
For each billing period:
- Work completed this period (per SOV)
- Plus: Approved change orders
- Less: Retainage (typically 5–10%)
- Less: Previous payments
- Equals: Current payment due
Retainage Explained
Retainage (retention) is a percentage withheld until project completion to ensure contractor finishes punch list items. Standard: 10% until 50% complete, then 5%.
Change Orders on Progress Bills
Each approved change order adds to the contract sum and appears as a separate SOV line item. Never perform extra work without a signed change order.
AIA G702/G703 Forms
Standard construction industry forms for payment applications. Even without formal AIA forms, follow the same logic: SOV, percent complete, retainage, net due.
Create Construction Invoices
Build detailed progress invoices with line items for each SOV category, retainage, and net payment due.